Study Process and Schedule
Study activities began in August 2009 and were completed in February 2011. There were four main phases to the project, which are shown in the figure below.Study Update
CATA and its study partners completed detailed discussions about three potential “Build AlternativesA Build Alternative is a proposed package of transportation improvements including a major transit investment. Each alternative is detailed enough so that comparisons can be made with other alternatives.” for the Michigan/Grand River Corridor: Bus Rapid Transit (BRT), Light Rail Transit (LRT), and Modern Streetcar. These discussions included an evaluation of their potential costs and benefits, as well as how they meet goals and objectives for the Corridor. From the beginning of the Study in the summer of 2009 through February 2011, the Study Partners identified and considered a large number of possible transit options for the Michigan/Grand River Corridor. On February 24th, 2010, several transit options, such as Personal Rapid Transit and Commuter Rail, were dismissed from further consideration because they did not meet criteria related to cost, ridership, environmental impact, consistency with local plans, and public support. The study partners completed a more in-depth evaluation phase of the three remaining alternatives to compare their costs and benefits. Activities included conceptual engineeringConceptual engineering identifies the basic components and needs of a project so that estimates of costs and impacts can be made., transit service planning, cost estimates and review of economic development potential. A fourth alternative, called the “Baseline Alternative”, was also developed for comparison purposes. The Baseline Alternative was a lower cost approach that attempted to address the needs of the Corridor without the significant infrastructure costs of each of the three Build Alternatives. This would include enhanced bus shelters at major stops, new park-and-ride facilities and the use of traffic signal prioritySignal priority means that traffic signal green time will be held longer for an approaching transit vehicle. Also, red time may be shortened if a bus is waiting. This is different from signal preemption, whereby a transit vehicle would always have a green condition. for buses. The Study Partners hosted open houses in November 2010 for the public to review and comment on the alternatives and the results of the evaluation. Public input was extremely important as the CATA Board expressed its support of BRT on Michigan/Grand River Avenues as the Locally Preferred Alternative (LPA)The LPA is an alternative that a local jurisdiction has concluded best meets a corridor's long-term transportation needs. If the Federal Transit Administration (FTA) believes the LPA has merit and is cost-effective, the agency will approve the project to advance into preliminary engineering. at their meeting on February 16, 2011. (See One-Pager #9 for more information on the LPA.) Now that an LPA has been selected, the next step is to apply to enter FTA’s Small Starts program. As part of the application process, CATA will conduct National Environmental Policy Act (NEPA) Scoping, the formal process that ensures citizens, elected officials, and appropriate government review agencies are involved early in the decision-making process and in outlining the scope of the study so comments and concerns can be addressed during the Project DevelopmentProject Development entails design, engineering, environmental clearance, refinement of costs, development of financial plan, negotiations and agreements, and construction plans. Project Development follows an Alternatives Analysis after a Locally Preferred Alternative has been selected.. In addition, the application process entails the following tasks:Study Material
Click here to review study material approved by the Steering Committee and Technical Committee. This material includes technical reports, memoranda and presentations.Purpose and Need
Click here to review the Purpose and Need Statement, which describes the problems, needs and opportunities being addressed by the Study.Goals and Objectives
Click here to review a set of goals and objectives that are helping guide the development and evaluation of corridor transportation options.Study Lingo
Click here to review a list of transportation planning terms that you may not be familiar with.